Although info from KCMO is scant, Platte Cty continues to plug along. A report was recently sent by Bob Heim (bheim@co.platte.mo.us) regarding an update. This is the piece of Barry Road from Potomac west to Chariton. Info includes, " The typical road section design is now complete and final construction drawings are expected to be complete by the end of October 2008 and "Twenty-five of the thirty property appraisals have been completed and the Right of Way/easement packages are being assembled by PCPW. Initial meetings with the property owners are expected to begin in October 2008." " MGE and AT&T have completed their relocation design work. Work for these contractors can begin once the Right of Way acquisition is complete.
Construction will occur after property acquisition, utility relocation and bidding is complete. Currently anticipate starting Phase I Construction Summer 2009.
Wednesday, October 22, 2008